Minimization the Power Losses in Wad Shaheen Substation Network of JDECo

dc.contributor.advisorZaro, Fouad
dc.contributor.authorALhassis, Bilal
dc.contributor.authorAlkhatib, Omar
dc.date.accessioned2021-09-16T07:14:49Z
dc.date.accessioned2022-05-22T07:28:52Z
dc.date.available2021-09-16T07:14:49Z
dc.date.available2022-05-22T07:28:52Z
dc.date.issued2021-06-01
dc.descriptionCD, no of pages 115 , طاقة 4/2021
dc.description.abstractThis project studies the distribution network of the Wad Shaheen substation by using Electrical Transient Analyzer Program (ETAP) and it aims to make the critical developments and improvements on the network to minimize the power losses. The network of the Wad Shaheen substation has high losses, during the average load, the power loss is 6.33% of demanded power this loss cost 4 ,299,408 NIS/Year. There are several techniques to reduce power losses in the distribution network, We chose two techniques to test their effectiveness on the network, as follows: - 1. Network reconfiguration. 2. Network reconductoring. After tested these techniques on the network, We found total power losses could be reduced from (1.636) MW to (1.382, 0.941 or 1.105)MW, depending on the soluition.en_US
dc.identifier.urihttp://localhost:8080/xmlui/handle/123456789/7214
dc.language.isoenen_US
dc.publisherجامعة بوليتكنك فلسطين - طاقةen_US
dc.subjectJDECoen_US
dc.subjectPower Lossesen_US
dc.subjectSubstation Networken_US
dc.titleMinimization the Power Losses in Wad Shaheen Substation Network of JDECoen_US
dc.typeOtheren_US

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Minmizing the Power losses in Wad Shaheen Substation Network of JDECO.Final report (1).pdf
Size:
3.93 MB
Format:
Adobe Portable Document Format

License bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Plain Text
Description: