Future development of electric power systems must pursue a number
of different goals. The power system should be economically efficient, it should
provide reliable energy supply and should not damage the environment. At the
same time, operation and development of the system is influenced by a variety
of uncertain and random factors.
In this study, data and statistics of the electrical network load were
collected from the Hebron distribution network within 5 years. The data and
statistics will entered to the ETAP software. The network will be analyzed during
peak periods, average loads, and summer time in order to obtain indicators of the
network losses and economic feasibility to reduce them. All substation data was
collected and then used to predict the load at each substation in 2050. The data of
photovoltaic (PV) system will be collected to study the amount of the energy
produced form the system, and then analyzed these data to estimate the power
will be produced.
Several scenarios will be developed to improve the network performance
and efficiency such as adding a main station or build a ring system. Some of the
substation was analyzed during peak periods, average loads, and summer time in
order to obtain indicators of the network losses and economic feasibility to reduce
them.
In addition, several solutions were developed to solve the problems by
adding main additional feeder to alduhdah substation to solve the problem of high
load |